Buying a new-build, off-plan or under-construction property in Italy can be an attractive route to a modern home with a defined specification, contemporary systems and a future completion date. It also means paying for a legal and physical result that may not yet exist when you sign.
For a foreign buyer, the risk is not limited to whether the developer will complete the building. The buyer needs to know who is selling, what has been authorised, what is included in the price, what protects advance payments, when delivery is actually due and what happens if the finished property differs from what was promised.
A brochure is not a contract. A rendering is not a building specification. A reservation payment is not harmless simply because the apartment, villa or development has been professionally marketed.
Govoni Law assists foreign buyers and investors purchasing off-plan, under-construction and newly built property throughout Italy. We work on the buyer’s side before a reservation fee, deposit, preliminary contract or construction-stage payment creates exposure.
Do not pay today for a future property until the legal protection is clear.
Request a pre-purchase legal review of your developer documents and proposed contract.
Short answer: is buying off-plan property in Italy safe?
Buying off-plan property in Italy can be legally protected, but the buyer should not assume that the necessary safeguards are automatically in place or adequate for the specific transaction.
Italian law can require substantial protections where a qualifying residential property is sold by a developer before completion, including a bank or insurance guarantee for certain advance payments and a post-completion insurance policy for serious structural defects. The precise application depends on the seller, the state of construction, the buyer’s status and the contract.
The buyer should verify the actual documents, rather than rely on labels such as “guaranteed”, “protected deposit”, “new development” or “developer sale”.
The essential question is not simply whether the project looks credible. It is whether the developer, property, payment structure, guarantees, specifications and contractual remedies protect the buyer before money is committed.
Before you sign: do not pay if
Do not transfer a reservation fee, deposit or stage payment until the buyer has received and reviewed the documents needed to understand the transaction.
Pause before proceeding if:
- You have received only a brochure, rendering, sales presentation or indicative floor plan.
- The developer asks for a reservation payment before supplying the full contract.
- The plan, terrace, garden, parking space or storage area is described informally rather than clearly identified in the contract.
- The contract allows broad changes to the layout, materials or specifications.
- The promised delivery date is vague or gives the developer broad extension rights.
- Advance payments are requested without clear written protection.
- You have been told that a guarantee exists but have not seen the guarantee itself.
- The issuer of a proposed guarantee has not been properly identified and checked.
- The price does not clearly state what is included, excluded or subject to variation.
- The developer’s legal identity, authority and title to the site have not been verified.
- Planning documents, approved drawings or construction-stage documentation are incomplete.
- You are asked to accept “equivalent materials” without a meaningful technical specification.
- You are relying on a promised sea view, parking space, pool, garden, storage room or guest accommodation that is not clearly incorporated into the agreement.
A new building is not automatically a simple building.
What are you actually buying from an Italian developer?
The expression “new build” can describe very different transactions. The buyer should understand the legal and physical stage of the property before deciding what protections are needed.
You may be buying:
- A property that exists only in plans, often described as off-plan.
- A unit in a development already under construction.
- A villa, apartment or residence that is close to completion but not yet ready for transfer.
- A recently completed property sold directly by the developer.
- A property with a promised future layout, garden, parking area, terrace, pool or common facilities.
- A purchase linked to staged payments during construction.
- A project in which the developer may still need to complete key works, infrastructure, common areas or documentation.
The buyer may be purchasing a future home, but legally the buyer is entering into a present contract.
That contract must identify the property precisely enough to protect the buyer if a parking space is moved, a terrace is reduced, a view is obstructed, materials are changed, delivery is delayed or promised common facilities are not completed as expected.
What should foreign buyers check before paying a developer?
The legal and financial review should cover more than the building itself. It should consider the developer, the site, the project, the money, the contract and the future delivery process.
| What to verify | Why it matters | What the buyer should request before signing |
|---|---|---|
| Developer identity and authority | The entity signing must have authority and capacity to sell the property | Full corporate identification, authority of signatories and transaction documents |
| Title to land and development | The developer must have a legally secure basis to build and transfer the property | Title documents, relevant land-registry information and project references |
| Planning and project documents | The property should correspond to an authorised development, not only a marketing concept | Available permits, approved plans, project documentation and relevant technical information |
| Exact unit and appurtenances | The buyer must know precisely what is included in the sale | Floor plan, cadastral or project identification, parking, storage, garden, terrace and common-area details |
| Price and tax treatment | The buyer needs a clear total cost and payment basis | Price breakdown, VAT treatment where applicable and a list of included and excluded items |
| Reservation payment | A “reservation” can create obligations and financial exposure | Reservation agreement, refund conditions, deadlines and payment destination |
| Payment schedule | Construction-stage payments should be clearly linked to contractual events and protection | Instalment schedule, payment triggers, deadlines and consequences of non-payment |
| Advance-payment guarantee | The buyer needs to understand whether and how early payments are protected | Full copy of the guarantee, issuer details, amount, duration and claim conditions |
| Delivery date | Delay can affect relocation, financing, rental plans and future commitments | Defined completion date, extension events, notice duties and remedies |
| Specifications | “Luxury finish” or “high quality” is not a legally precise obligation | Detailed capitolato, materials, systems, brands, quality standards and exclusions |
| Variations and extras | The developer may otherwise retain broad freedom to alter the result or add cost | Rules for changes, equivalent materials, buyer approval and pricing |
| Final handover | Buyers need a clear route from completion to keys and final deed | Handover procedure, inspection rights, defect reporting and completion documents |
| Insurance and warranties | New construction can still involve serious or ordinary defects after completion | Required insurance and warranty documentation, delivered at the appropriate stage |
This is the level of detail that turns a future property into a legally intelligible transaction.
What is a fideiussione and why should a buyer verify it?
When a qualifying residential property is sold by a developer before completion, Italian law may require the developer to provide a bank or insurance guarantee, commonly called a fideiussione, for sums paid by the buyer before the final deed.
The purpose is to protect advance payments if the developer faces a qualifying crisis or cannot complete the transaction in the manner required by law.
The buyer should not treat the word “guarantee” as sufficient. The relevant protection should be reviewed in its actual form.
A serious buyer should verify:
- Whether the transaction falls within the legal framework requiring a guarantee.
- The legal identity of the entity issuing the guarantee.
- Whether the issuer is authorised and appropriate for the guarantee being provided.
- The amount covered by the guarantee.
- Whether it covers all relevant sums paid before the final deed.
- The date on which the guarantee begins and ends.
- Whether the buyer is correctly identified.
- The conditions and procedure for making a claim.
- Whether the preliminary contract accurately refers to the guarantee.
- Whether further payments are requested before the buyer has received adequate documentation.
Foreign buyers can easily assume that a document called a fideiussione is automatically valid, enforceable and sufficient. That assumption can be dangerous.
In practice, the buyer may receive a document that is incomplete, poorly connected to the transaction, issued by an entity whose standing requires verification, limited to an amount below the planned payments, subject to unclear conditions or drafted in a way that does not match the contract.
A guarantee should be checked before the money is transferred, not tested after a dispute begins.
Do not rely on the word “guaranteed”. Ask to see the actual guarantee.
Is escrow the same as a fideiussione?
No. A fideiussione and an escrow arrangement are different forms of protection.
A fideiussione is a guarantee that may protect the buyer’s advance payments in qualifying developer transactions. An escrow arrangement generally concerns funds held by an independent third party under agreed release conditions.
The presence of one does not automatically mean that the other exists. A buyer should not assume that a developer’s statement that funds are “protected” or “held safely” describes a formal escrow structure or legally sufficient guarantee.
The buyer should ask:
- Who receives the money?
- In whose account is it held?
- Who can release it?
- What contractual event permits release?
- What happens if construction is delayed or does not proceed?
- What protection applies if the developer becomes unable to perform?
- Is the payment method consistent with the preliminary contract and legal safeguards?
Govoni Law does not hold itself out as a general escrow provider for developer sales. Where an escrow structure may be appropriate, the buyer should assess the legal and contractual arrangement before funds are moved.
For transactions where payment protection requires focused attention, see Escrow Property Purchases in Sardinia.
What should the preliminary contract with a developer include?
The preliminary contract is not a formality between reservation and completion. It is the document that allocates the buyer’s money, time and legal protection during the construction period.
A buyer should not accept a developer’s standard form simply because it appears detailed or has been prepared by an Italian professional. The buyer needs to understand whether the contract adequately identifies the property, payment obligations, delivery date, guarantees, specifications and remedies.
A buyer-side review should consider whether the preliminary contract clearly addresses:
- The identity and legal capacity of the developer.
- The precise property being sold.
- The relevant plans and the status of the project.
- The purchase price and VAT treatment where applicable.
- The timing, amount and purpose of every payment.
- The legal treatment of the reservation fee and deposit.
- The advance-payment guarantee and its terms.
- The detailed capitolato of materials, finishes, systems and equipment.
- Parking spaces, storage rooms, gardens, terraces, balconies and common areas.
- The delivery date and the circumstances in which it may be extended.
- The buyer’s rights if delivery is delayed.
- The buyer’s rights if the developer changes the project or materials.
- The rules for buyer-approved extras or variations.
- The documents to be delivered before the final deed.
- Handover, inspection and defect-reporting procedures.
- The insurance documentation required at the final deed where applicable.
- The buyer’s remedies if essential obligations are not fulfilled.
The contract should state what the developer must deliver. A brochure should not be allowed to carry the most important promises outside the contract.
For buyers who have received a proposed agreement, Review and Negotiation of Purchase Offers and Preliminary Contracts can provide focused legal support before signature.
Can a developer change the plans, materials or delivery date?
The answer depends on the contract, the project documents, the nature of the change and the circumstances.
A developer may need some flexibility during construction. The buyer should nevertheless distinguish between a reasonable technical adjustment and a change that reduces the property’s value, use, layout, quality or practical suitability.
The buyer should not accept vague terms allowing the developer to substitute materials, change layouts or alter common areas without understanding the limits of that discretion.
Particular care is needed where the buyer’s decision depends on:
- A sea view or orientation.
- A terrace or private garden.
- A parking space or garage.
- A storage room.
- A specific number of bedrooms or bathrooms.
- A separate guest area.
- A pool or shared amenity.
- Energy performance.
- Accessibility.
- A premium material or technical specification.
- A delivery date connected with relocation, retirement, financing or rental plans.
A buyer may be willing to accept a limited substitution of material where the quality is objectively equivalent. That does not mean the buyer should accept an undefined right for the developer to deliver something materially different from what was sold.
What happens if completion is delayed?
Delay is one of the central risks in an off-plan purchase.
A future delivery date can affect relocation plans, school arrangements, mortgage timing, rental commitments, family plans and the buyer’s ability to sell or leave their current home. For a foreign buyer, delay can also mean ongoing travel, temporary accommodation and extended uncertainty.
The buyer should not be satisfied with a generic reference to expected completion.
The contract should make clear:
- The agreed delivery date.
- What counts as completion.
- Which events can justify an extension.
- How the developer must notify the buyer of a delay.
- Whether there is a maximum extension period.
- What remedy applies if delivery is materially delayed.
- Whether the buyer can claim compensation, require performance or terminate in defined circumstances.
- What happens to payments already made.
- Whether delay affects the final deed deadline.
- Which documents and certifications must be available before the buyer accepts handover.
A delivery date that can be extended indefinitely is not a meaningful protection.
Why a finished-looking development can still create buyer risk
A development may look almost complete during a visit. It may still have legal, documentary or contractual matters that need attention before the buyer pays the balance or accepts the keys.
The buyer should not assume that “almost finished” means “ready to buy”.
Potential issues may include:
- Differences between the approved project and the completed building.
- Common areas, landscaping, roads, utilities or amenities that are unfinished.
- Parking, storage or external areas not clearly allocated.
- Works or features represented in marketing materials but not reflected in the contract.
- Delayed certificates, permits or completion documentation.
- Construction deviations that affect the buyer’s unit.
- Unclear condominium structure, costs or management arrangements.
- Defects visible at handover.
- Missing or inadequate warranty and insurance documentation.
- Mortgages, financial arrangements or registered burdens affecting the developer’s property that require an orderly release before transfer.
The buyer needs to know not only whether the apartment or villa looks complete, but whether the legal file is complete enough for the buyer to accept the property safely.
What should happen before the final deed and handover?
The final deed before the notary should not be the first time the buyer sees essential documents.
Before the final signing, the buyer should normally have clarity on:
- The final identity and description of the property.
- The purchase price and payment balance.
- The documents required for the transfer.
- The status of any mortgage, lien or burden to be cancelled.
- The applicable guarantees and insurance documentation.
- The planning and cadastral position of the completed property.
- The final technical specification and any agreed variations.
- The condition of the property on handover.
- Visible defects, incomplete works or issues requiring formal reservation.
- The timing of keys, possession, utilities and any final obligations.
A buyer should arrange an appropriate inspection of the completed property before accepting it, particularly where the buyer has purchased remotely or has not been able to follow the construction process.
Govoni Law does not provide engineering, architectural or surveying opinions. Where technical inspection is required, the buyer should involve an appropriately qualified professional. Our legal role is to ensure that the legal and contractual implications of any identified issue are understood and addressed before acceptance.
A practical example: buying off-plan in Bordighera
A British buyer identifies an apartment in a new coastal development in Bordighera. The delivery date is expected in approximately eighteen months.
The brochure promises sea views, a large terrace, premium finishes, energy-efficient systems, a private parking space and access to landscaped common areas. The buyer is asked to sign a reservation agreement and pay an initial sum, followed by a substantial payment at the preliminary contract stage.
Before committing, the buyer should establish:
- Which company is the developer and who has authority to sign.
- Whether the developer has the legal basis to build and sell the unit.
- Which approved plans correspond to the apartment being purchased.
- Whether the terrace, parking space and common facilities are contractually identified.
- Whether the view and layout are contractual commitments or merely marketing statements.
- Which sums are payable before the final deed.
- What protection applies to every advance payment.
- Whether the proposed guarantee is issued by an appropriate institution and covers the required amount and period.
- Whether the specification document clearly identifies materials, systems and included items.
- What happens if materials, floor plans or completion dates change.
- What documents and insurance must be delivered before the final deed.
- What remedy the buyer has if completion is delayed or the delivered apartment differs materially from the agreed specification.
The buyer is not simply choosing a new apartment. The buyer is entering a contract that allocates money, time, construction risk and legal remedies over the next eighteen months.
What Govoni Law does before you pay a developer
Govoni Law assists foreign buyers and investors purchasing off-plan, under-construction and newly built property throughout Italy.
Our work is buyer-side and legal-first. We review the transaction before the buyer’s money and contractual position become exposed.
Depending on the stage and complexity of the purchase, our work may include:
- Reviewing the developer’s identity, authority and available transaction documents.
- Identifying legal and documentary red flags before a reservation fee or deposit is paid.
- Reviewing the legal framework and documents supporting advance-payment protection.
- Reviewing the preliminary contract, payment schedule, delivery terms and buyer remedies.
- Assessing whether plans, specifications, parking, terraces, gardens and other material features are properly incorporated into the transaction.
- Reviewing legal questions arising from title, project documentation and available permits.
- Identifying matters that require review by an appropriately qualified technical professional.
- Reviewing and negotiating purchase offers and preliminary contracts.
- Helping the buyer understand whether to proceed, renegotiate, require conditions or walk away.
- Coordinating, where appropriate, with the notary, technical professionals and other qualified advisers involved in the transaction.
If you have received a brochure, reservation agreement, draft preliminary contract or payment schedule, the Before You Sign Brief for Foreign Buyers in Italy can provide a focused first written assessment of the immediate risks and next steps.
If a specific contract, guarantee, delivery clause or payment structure requires detailed attention, Review and Negotiation of Purchase Offers and Preliminary Contracts may be the appropriate route.
For a serious acquisition involving developer due diligence, title, project documents, payment protections, contract terms and wider property risk, Full Legal Due Diligence for Property Buyers in Italy provides the fullest buyer-side review before commitment.
The right level of legal protection depends on the decision you are about to make.
What Govoni Law does not do
Govoni Law does not sell new developments, act for developers, guarantee construction completion, provide construction-management services, issue engineering or architectural opinions, inspect structural works as a technical professional, arrange mortgages or provide personalised tax advice.
We do not guarantee that a developer will meet every future deadline or that a property will appreciate in value.
Where tax, financing, structural, architectural, engineering, insurance or construction-supervision advice is required, the buyer should involve the appropriate qualified professional.
Our role remains clear: to protect the buyer’s legal position before the buyer pays, signs or accepts the future property.
Checklist: buying off-plan property in Italy
Before paying a reservation fee, deposit or stage payment, consider whether you have:
- Identified the exact developer entity and the person authorised to sign.
- Requested the available title, project and planning documents.
- Confirmed the exact unit, floor plan, terrace, garden, parking space, storage room and common facilities included in the sale.
- Read the full reservation agreement or preliminary contract before payment.
- Checked the amount, timing and legal effect of every payment.
- Requested and reviewed the actual advance-payment guarantee where applicable.
- Verified the identity, standing, amount, duration and claim terms of the issuer.
- Confirmed the stated delivery date and the developer’s extension rights.
- Obtained a detailed capitolato of materials, systems, finishes and included items.
- Reviewed variation clauses, substitute-material provisions and extra-cost mechanisms.
- Identified the buyer’s remedies for delay, material changes or non-delivery.
- Understood which documents, insurance and certificates must be available before the final deed.
- Planned an appropriate inspection before accepting handover.
- Obtained legal review before the reservation, deposit or preliminary contract becomes binding.
Frequently asked questions
Can foreigners buy off-plan property in Italy?
Yes, foreign buyers can often purchase off-plan or newly built property in Italy, subject to the applicable rules for their nationality, status and the specific transaction. The buyer should verify the purchase structure, developer documents, payment protections and contract before committing.
Is a deposit safe when buying from a developer in Italy?
A deposit or advance payment should not be treated as automatically safe. In qualifying transactions, legal protections may apply, including a bank or insurance guarantee for certain payments made before the final deed. The buyer should review the actual guarantee, contract and payment terms before money is transferred.
What is a fideiussione in an Italian off-plan purchase?
A fideiussione is a bank or insurance guarantee that may protect advance payments made by the buyer before the final deed in qualifying developer transactions. The buyer should verify the issuer, coverage, amount, duration and claim conditions before relying on it.
Do I need a lawyer before signing a reservation agreement with an Italian developer?
A reservation agreement can create financial and contractual exposure. A buyer should understand the refund terms, deadlines, payment destination, obligations and missing documents before signing or transferring a reservation payment.
What happens if the developer delivers late?
The buyer’s position depends on the contract, stated delivery date, permitted extension events and available remedies. These matters should be addressed clearly before the preliminary contract is signed.
Can a developer change the floor plan or materials after I sign?
The answer depends on the contract and the nature of the change. A buyer should review clauses dealing with variations, equivalent materials, layout changes, specifications, common areas and the remedy for a material departure from what was agreed.
What documents should I ask for before buying a new-build property in Italy?
You should request the proposed contract, payment schedule, available project and planning documents, detailed technical specifications, information identifying the developer and property, documentation concerning advance-payment protection where applicable, and the documents required for final delivery and transfer.
Do I still need legal due diligence if the property is new?
Yes. A new property can reduce some risks associated with an older building, but it creates different risks involving the developer, project documents, payment protections, contract terms, delivery, specifications, variations, defects and future transfer.
If you are considering an off-plan, under-construction or new-build property in Italy, contact Govoni Law before paying a reservation fee, deposit or stage payment.
Send the brochure, floor plans, proposed contract, payment schedule, guarantee documents and available project information. We will assess the legal risks before you commit.
A new property can reduce some risks of an older home, but it creates a different one: paying today for a legal and physical result that will only exist tomorrow.