Office-to-Residential Conversion in Milan: What Can Go Wrong

Milan has thousands of offices, ground-floor shops and former workshops that are being turned into apartments and lofts. For buyers, they can look like an opportunity: central locations, high ceilings, large windows, often lower prices than traditional flats. For investors, converting an office looks like a way to create value.

Both can work. But a converted office is only a home if the change of use was lawfully made and the space meets the standards required for living. If not, you may be paying a residential price for a property that is, legally, still an office.

In Milan, a converted office can look exactly like an apartment. Only the file shows whether it is one.

Short answer: what can go wrong?

The most common problems are:

  • The change of use was never properly filed, or does not match the works actually carried out.
  • The space does not meet residential standards for height, light, ventilation or layout.
  • The cadastral category was updated, but the planning position was not.
  • Local rules or the building’s mix of uses limit the change.
  • The wider project is under investigation, and the building’s permits are being questioned.
  • Condominium rules restrict residential use, or the shared costs are designed for offices.

Each of these can affect your ability to live in the property, rent it, obtain a mortgage, claim first-home tax benefits or resell it.

What changed with the 2024 “Salva Casa” rules

In 2024, Italy simplified the rules on changing the use of individual units. Today, a single unit in the main urban zones of a city (zones A, B and C) can generally change between residential, tourist-accommodation, office-production and commercial use. When no building works are involved, this requires a certified notice to the municipality, known as a SCIA.

This has made many conversions easier. It has also created a common misunderstanding: “always allowed” does not mean “automatic”. The change must still:

  • Be filed correctly, with the right procedure for the works actually done.
  • Respect the specific conditions that municipal plans can set.
  • Comply with health, safety and building standards for residential use.
  • Take into account the use that prevails in the other units of the building.

If works were carried out, such as new bathrooms, a kitchen, new internal walls or a mezzanine, they need their own authorisation.

Problem 1: the change of use exists only on paper, or not at all

A seller may say the unit was “converted to residential”. Ask what that means in documents:

What you are toldWhat it may actually mean
“It’s residential now”The cadastral category was changed, but no planning filing was made
“There’s a SCIA”A filing exists, but it may not cover the works actually done
“The previous owner lived here for years”It was used as a home, not necessarily authorised as one
“The agency handled it”Ask for the filing, its date, its content and its outcome

The cadastral category, for example from A/10 (office) to A/2 or A/3 (residential), is a tax record. It does not prove that the municipality authorised the change. Compare the cadastral record with the municipal building file. See What Does “Regular” Mean When Buying Property in Italy?

Problem 2: it is not habitable by residential standards

Offices and homes have different requirements. A space that is fine for desks may not meet the standards for living space, especially in:

  • Ceiling height, particularly in mezzanines and lowered areas.
  • Natural light and ventilation in bedrooms and living areas.
  • Bathrooms and kitchens, including drainage and extraction.
  • Basements and ground floors facing a courtyard.

A qualified local technician should check the space against the residential standards that apply. If a room does not qualify as a bedroom, it should not be priced as one.

Problem 3: local conditions and the building’s prevailing use

National rules allow municipalities to set specific conditions, and give weight to the use that prevails in the rest of the building. A single apartment in an office building, or a converted shop in a building with specific restrictions, may face limits that a converted office in a residential block would not.

Ask your technician to check the municipal plan and the building’s overall use before you rely on the change.

Problem 4: the project is part of the Milan planning investigations

Since 2023, the Milan prosecutor’s office has been investigating a number of real estate projects. The main allegation is that new buildings were authorised as “renovations” through simplified procedures instead of the permits required for new construction. Several construction sites have been seized, others stopped, and some buyers who had signed preliminary contracts for new or converted homes have been left waiting.

The legal debate is ongoing, and courts have not always agreed with the prosecutors. The point for a buyer is practical: if a project’s permits are being questioned, your purchase can be delayed or blocked, even if you did nothing wrong.

Before signing for a converted or redeveloped building, check:

  • Which permit or filing authorised the project.
  • Whether the project, the developer or the site is involved in any investigation or seizure.
  • What the contract says if completion is delayed or blocked by public authorities.

For off-plan and developer purchases, read Buying From a Developer: Legal Guarantees and Protections.

Problem 5: the condominium was built for offices

In a building that was designed for offices, the condominium may still be organised around commercial use. Check:

  • Whether the condominium regulation restricts residential use or certain activities.
  • How costs for heating, lifts, security and maintenance are shared.
  • Whether other units are still offices, and what that means for noise, opening hours and services.
  • Any approved works to adapt the building.

See Buying an Apartment in Italy? 9 Condominium Documents to Check.

If you plan to convert an office yourself

Investors buying an office to convert should check feasibility before the offer:

  • Is the unit in a zone and a building where the change is allowed?
  • Will the works needed require more than a simple notice?
  • Can the space meet residential standards after the works?
  • What fees or contributions will the municipality charge?
  • Is the building or the plot affected by any restriction or investigation?

Price the office as an office until feasibility has been confirmed. For a broader view of investment checks, see Invest in Italian Real Estate: A Lawyer’s Guide.

What the offer must say

If you are buying a converted unit, the offer should normally include conditions tied to:

  • Delivery and review of the change-of-use filing and the building file.
  • Consistency between the current layout and the authorised works.
  • Compliance with the residential standards relied on in the price.
  • The absence of seizures or proceedings affecting the building’s permits.
  • The return of your deposit if a condition fails.

Read Caparra vs Deposit When Buying Property in Italy.

A practical example: a loft in Isola

A couple from London finds a two-bedroom loft in Isola, in a former printing workshop converted in 2022. The listing describes it as residential. The cadastral category is A/2.

The building file tells a more complex story. The change of use was filed for the ground floor, but the mezzanine with the second bedroom was added afterwards with no filing. Its ceiling height also does not meet the standard for a bedroom. The rest of the building is mainly offices.

The couple still buys the loft, but as a one-bedroom unit with a mezzanine used as a study, at a price that reflects it. The offer includes a condition on the delivery of the full building file.

Checklist before you sign

  • I have the change-of-use filing, not only the cadastral category.
  • The filing covers the works actually carried out.
  • A technician has checked the residential standards.
  • I know the use that prevails in the rest of the building.
  • I have checked for seizures or investigations affecting the project.
  • The condominium regulation allows residential use.
  • The offer protects my deposit if a condition fails.

How Govoni Law helps

Govoni Law acts only for buyers. For converted offices and redeveloped buildings in Milan, we review the building file, the change-of-use filing, the condominium documents and the contract, and coordinate with a local technician for the residential standards. We tell you in writing whether the property you are paying for is lawfully a home, and how the offer should protect you.

We do not design conversions, certify habitability or guarantee planning outcomes.

Your stageUsual levelService
You have a listing or a draft offerA first written assessmentBefore You Sign Brief
One issue needs an answer, such as the change of useA focused reviewLight Due Diligence
You are committed to the purchaseA full investigationFull Legal Due Diligence

For buying in Milan generally, see Property Lawyer in Milan for Foreign Buyers.

Frequently asked questions

Can you convert an office into an apartment in Milan?
Often yes. Since 2024, a single unit in the main urban zones can generally change to residential use with a certified notice, subject to municipal conditions, residential standards and any works requiring their own authorisation.

If the cadastral category is residential, is the conversion legal?
Not necessarily. The cadastral category is a tax record. You need the municipal filing for the change of use and for the works.

What are the minimum requirements for a converted office to be a home?
The space must meet the residential standards for height, light, ventilation and services. A local technician should check them.

How does the Milan planning investigation affect buyers?
If a project’s permits are questioned, construction or completion can be delayed or blocked. Check the project’s status and protect yourself in the contract.

Can I get a mortgage on a converted office?
Banks usually require a lawful residential unit. An unclear change of use can affect financing.


Buying a converted office in Milan, or planning a conversion? Send us the listing, the documents and the draft offer. We will do our best to reply to your request as soon as possible and tell you in writing whether the property is lawfully what you are paying for.